A Japanese power company is turning its own plant into a $15 billion AI computer
JERA, Dell and RHAELM plan to build a data centre directly at an existing power plant, skipping the grid queue that is slowing AI buildouts everywhere else.
Two suppliers detailed their own share of a four-supplier deal a trade publication puts above 1.7 gigawatts. The part that matters is that none of it is new construction.
The Ratepayer Protection Act would make data centres, not ordinary households, cover the cost of new grid infrastructure built to serve them. It cleared committee 52 to 0 and the House almost unanimously.
Strata, the whole AI stack, explained simply. Every number carries a source and a confidence label.